EN

EN

News

Home News The complete process of launching a large-scale slide project: 10 key stages from concept design to safe operation

The complete process of launching a large-scale slide project: 10 key stages from concept design to safe operation

Date:2026-02-06    Click:7

The complete process of launching a large-scale slide project: 10 key stages from concept design to safe operation

Successfully implementing a large-scale slide project is far more than just "purchasing and installing equipment". It is a complex system engineering project that involves multiple dimensions such as creativity, engineering, safety, and operation. This guide breaks down the large-scale slide project into 10 key stages, providing a clear roadmap for investors, developers, and operators to ensure that the project can be safely, efficiently, and perfectly realized from concept to reality. 

Phase 1: Conceptualization and Feasibility Analysis (Concept & Feasibility)

This is the "birth" stage of the project's core concept, with the core question being "Why do we do this and can it be accomplished?" 

Market positioning: Who are the target customers? (Families and children? Young tourists?) And the complementary relationship with other facilities within the park? 

Initial idea: Sliding type (high-speed, rotating, interactive?), theme storyline, desired visitor experience. 

Site preliminary survey: assessment of usable area, terrain elevation difference, geological conditions, surrounding environment and visual analysis. 

Financial projection: Initial investment scope (equipment, infrastructure, soft furnishings), investment return rate (ROI) forecast. 

Output: "Project Concept Proposal" and "Preliminary Feasibility Analysis Report". 



Phase Two: Professional Consultation and Scheme Deepening (Design Development)

Introduce professional expertise to transform the concept into a feasible technical solution. 

Select professional suppliers: Look for amusement equipment companies that have international certifications (EN1176, ASTM), a wealth of case studies, and design capabilities. 

Joint design of the scheme: Work together with the designers and engineers of the suppliers to determine: 

Core parameters: precise height, length, slope, gliding speed. 

Three-dimensional layout: slide path, starting and ending points, queuing area, viewing platform. 

Theme Enhancement: Design, Color, Packaging Materials, Interactive Elements (Lighting, Sound Effects, Sprays). 

Output: 3D renderings, preliminary floor plan diagrams and technical specification documents. 



Phase 3: Compliance Approval and Security Certification (Compliance & Certification)

Ensure that the project operates smoothly in terms of both legal and security aspects. 

Local regulations verification: Seek information on construction application requirements from the planning, construction, market supervision, and fire protection departments. 

Safety standard lock-in: Clearly define the mandatory standards that the project must follow (such as GB/T 27689 in China, and EN 1176 in the EU). 

Third-party certification pre-review: Invite authoritative testing institutions (such as TÜV, SGS) to conduct a preliminary review of the design plan to ensure a successful final acceptance in one go. 

Output: Compliance checklist and pre-certification opinion letter. 



Phase 4: Detailed Design and Engineering Drawings (Detailed Design)

"The blueprint stage" serves as the sole basis for manufacturing and construction. 

Structural engineering design: The load calculations for the supporting structure, foundation design, and seismic and wind resistance analysis are completed by registered structural engineers. 

Manufacturer's deep design: The supplier provides a complete set of processing and manufacturing drawings for factory production. 

Civil construction coordination design: Provide precise drawings for equipment foundations, embedded parts, drainage, and electrical connection points. 

Output: Complete set of construction drawings, structural calculation documents and Bill of Materials (BOM). 

Phase 5: Manufacturing and In-Plant Testing (Manufacturing & Factory Acceptance Test)

Quality is created in the factory, not fixed on-site. 

Material procurement and processing: Supervising the sources and quality of core materials (such as fiberglass reinforced plastic, stainless steel, and special plastics). 

Production process supervision: Regularly check the production progress and processes of the factory (such as the laminating process of fiberglass reinforced plastic, weld quality). 

In-plant pre-assembly test (FAT): Before shipment, invite the customers to visit the factory for acceptance inspection, and conduct trial assembly and functional tests of key components. 

Output: Product quality certification documents, FAT test reports and packaging and shipping plans. 

Phase 6: Site Preparation and Foundation Construction (Site Preparation)

"Great buildings rise from a solid foundation", and the foundation determines long-term stability. 

Site clearance and leveling. 

Follow the plan: Pour the reinforced concrete foundation and precisely install the pre-installed components (this is the key to the success or failure of the installation!) 。


Public facility pre-installation: Installation of power, drainage, communication and other pipelines. 

Output: Basic Engineering Acceptance Report (signed and confirmed by the supplier). 

Phase 7: Equipment Installation and Mechanical Completion

This is the core stage, and the professional installation team is of utmost importance. 

Component hoisting and assembly: The installation is carried out by a team certified by the supplier, ensuring that each step complies with the process requirements. 

Structural adjustment: Ensure that all supporting columns are vertical, connections are tight, and the sliding track joints have a smooth transition. 

Initial debugging: Check the smoothness of the slide, test the lighting, water spraying and other auxiliary systems. 

Output: Installation process records and mechanical completion confirmation documents. 

Phase 8: Final Inspection, Certification and Trial Run (Final Inspection & Commissioning)

The stage where the "license" for safe operation is obtained. 

Third-party final inspection: By an authoritative institution for on-site testing, a compliant inspection report or a safety certification certificate will be issued. 

Load and safety test: Use sandbags to simulate full-load operation and test the emergency stop system (if any). 

Trial operation (SOP verification): Staff members conduct multiple-day trial runs following the standard operating procedures, and record all the data. 

Output: Safety certification certificate, trial operation report, and operation and maintenance manual. 

Phase 9: Staff Training & Soft Opening

The transition from "equipment" to "experience" hinges on the people. 

Graded Training: 

Operator: Equipment start-stop, daily inspection, emergency handling. 

Waiter: Tourist guidance, rule explanations, posture corrections. 

Maintenance technician: Regular maintenance procedures, troubleshooting common faults. 

Operational materials in place: safety signs, queue guidance signs, emergency response signs, and visitor information. 

Soft launch: Invite a small number of real tourists for stress testing and improve the operation procedures. 

Output: Training qualification records, complete operational SOP documents, and opening inspection checklist. 

Phase 10: Long-term Maintenance and Continuous Optimization

The implementation of the project is not the end; rather, it marks the beginning of safe and profitable operation. 

Carry out preventive maintenance plans: daily, weekly, monthly and annual inspection and maintenance tasks. 

Key component life management: Establish a replacement record for vulnerable parts (such as gaskets, sensors). 

Data-driven optimization: Collect data such as passenger flow, queuing time, equipment failure rate, etc., for future renovation or marketing decisions. 

Regular re-inspections: In accordance with regulatory requirements, arrange annual or regular third-party safety inspections. 

Output: Digital maintenance logs, annual safety assessment reports, and continuous improvement plans. 

The key to success: Manage the slide project like you manage a construction project.

The essence of a large slide is a special steel structure structure. The secret to success lies in: 

Front-end deep involvement: The operation team should get involved from the very beginning of the concept stage to ensure that the design meets the actual operational requirements. 

Single responsible party: Try to choose the general contractor that offers "design - manufacture - installation - certification" integrated services, to avoid disputes among multiple parties. 

Allocate sufficient time: From design to opening, it is reasonable and necessary to reserve 6 to 12 months for a large and complex slide. 

The budget takes into account "full life cycle cost": The initial investment should include the costs for core component replacements and regular certifications over the next 10 years. 

By following these ten stages, you will not only obtain a cool amusement facility, but also acquire a long-term asset that is safe and reliable, operates efficiently, is durable, and has a clear return on investment. This is precisely the core path for a professional slide project to evolve from "a fleeting trend" to "lasting classic status".

Copyright © 1993-2023 白鹿集团有限公司 版权所有

bailuyoule@gmail.com